Construction Updates

Campus Wide

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Storm Water In Design TBD Dec-25 Planning & Construction Randy Vaughn vaughd@marshall.edu Shock & Awe project
Campus Fire Alarm Upgrade Fire Alarm Upgrade in Corbly Hall, Myers Hall, Morrow Library, Smith Hall, SMB Feb-24 Dec-25 Health & Safety Daniel Persinger persing3@marshall.edu Shock & Awe project

Corbly Hall

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Corbly Hall Elevator Elevator Modernization late Aug./Sept. Dec-25 Elevator will be out of service TBD Planning & Construction Becky Lusher lusher30@marshall.edu Shock & Awe project
Classroom Repair Repair the majority of classrooms in Corbly Hall May-24 Aug-25 Work on floors 2-4 Facilities and Operations Bill Black blackb@marshall.edu Shock & Awe project

Drinko Library

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Drinko Roof Replacement replace roof Dec-25 College Ave and Drinko receiving will be blocked intermittently. Planning & Construction Randy Vaughn vaughd@marshall.edu Shock & Awe project

Fine Arts Building

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Fine Arts Reno Updates Feb-24 Dec-25 Main lobby will be out of service during non-event times Planning & Construction Scott Morehouse morehou1@marshall.edu Shock & Awe project

Gullickson Hall

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Gullickson Hall Roof roof replacement started Dec-25 18th st. is scheduled to be closed 8/11 Planning & Construction Scott Morehouse morehou1@marshall.edu Shock & Awe project
GH WR Fuel Center Buildout new student-athlete “”Fuel Center” snacks/shakes/supplements “ TBD TBD Athletics Andrew Brown brown613@marshall.edu Private – BG

Harris Hall

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Harris Hall Elevator Elevator Modernization late Aug./Sept. Dec-25 Elevator will be out of service TBD Planning & Construction Becky Lusher lusher30@marshall.edu Shock & Awe project

Henderson Center

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Henderson Center HVAC on hold on hold Planning & Construction
Henderson Center Sanitary Level E sanitary pipe replacement start after baseball Dec-25 restrooms will be temporarily closed Planning & Construction Scott Morehouse morehou1@marshall.edu Shock & Awe project
HC Pool Pump Circulation pump has failed Apr-25 Jun-25 Pool remains unusable until repair is completed Facilities and Operations Larry Metcalf metcalfl@marshall.edu University
Arena Floor – Henderson New basketball/volleyball floor in Cam Henderson Center Arena TBD TBD Athletics Andrew Brown brown613@marshall.edu Athletic Budget
HC Pathway Improvements Henderson Center SA Pathways – continued graphic & aesthetic improvements (A & C levels) 25-Jun 25-Jul Athletics Andrew Brown brown613@marshall.edu Private – BG

Holderby Hall

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Holderby Hall Demo Demo May-25 Oct-25 Building is down. MUPD will be working on blocking off area for those moving into Buskirk. Planning & Construction Jeff Pratt pratt65@marshall.edu Shock & Awe project

Institute for Cybersecurity

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Institute for Cyber Security This new building will be located directly across Hal Greer Boulevard from the university’s Old Main, the building will serve as the west gateway to the Fourth Avenue Innovation corridor, currently under development by Fairmount Properties. TBD TBD Will have impact on and around the property located on 4th Ave. Details to follow. Planning & Construction Scott Morehouse morehou1@marshall.edu

Memorial Student Center

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
MSC Chiller replace student center chiller Sep-25 Planning & Construction Randy Vaughn vaughd@marshall.edu
MSC Restrooms Repairs & Reno Full demo and remodel of 1st floor restrooms Jul-25 1st’floor restrooms closed Planning & Construction Jarrett Smith smith1866@marshall.edu Shock & Awe project

Morrow Library

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Morrow Library ADA Upgrades updates to comply with ADA standards Dec-25 Elevator will be shut down for a period of time. TBD Planning & Construction Scott Morehouse morehou1@marshall.edu Shock & Awe project

South Charleston Campus

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
South Charleston Roof Academic Bldg Replace roof Feb-24 Dec-25 rear stairwell is closed until further notice Planning & Construction Scott Morehouse morehou1@marshall.edu Shock & Awe project
South Charleston Roof Administration Bldg Replace roof Feb-24 Dec-25 Planning & Construction Scott Morehouse morehou1@marshall.edu Shock & Awe project

Old Main

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Old Main Structural Repairs Updates Dec-25 Restrooms in basement will be temporarily closed. Planning & Construction Randy Vaughn vaughd@marshall.edu Shock & Awe project

Prichard Hall

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Prichard Hall Single Passenger Elevator Replacement replace elevator that is centrally located on the east side of the building TBD Elevator will be out of service TBD Planning & Construction Scott Morehouse morehou1@marshall.edu
Prichard Hall Generator Install new generator Power will be shut off 2-3 hours. Date/time TBD. Planning & Construction Randy Vaughn vaughd@marshall.edu

Public Safety

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Public Safety Emergency Generators install emergency generator Jan-24 on hold Planning & Construction Randy Vaughn vaughd@marshall.edu Shock & Awe project

Science Building

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Science Bldg Air Handler Units Install new units May-25 Dec-25 Fence and laydown area will be moved the week of the 19th to help with parking. Planning & Construction Randy Vaughn vaughd@marshall.edu Shock & Awe project
Science Building Elevator Elevator Modernization late Aug./Sept. Dec-25 Elevator will be out of service TBD Planning & Construction Becky Lusher lusher30@marshall.edu Shock & Awe project

Shewey Building

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Shewey South Roof Planning & Construction Scott Morehouse morehou1@marshall.edu
Shewey Deck Deck & premium space buildout inside and outside Shewey building 25-Apr 25-Aug Athletics Andrew Brown brown613@marshall.edu Private
Shewey EQ Room – Issue Cubbies Removal of current EQ space issue cubbies, installation of two new sets TBD TBD Athletics Andrew Brown brown613@marshall.edu Private – BG

Smith Business

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding

Smith Communications

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding

Smith Hall

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Smith Hall Single Elevator Replacement replace elevator that is centrally located TBD Elevator will be out of service TBD Planning & Construction Scott Morehouse morehou1@marshall.edu
Smith Hall and Fine Arts locks Replace all locks due to antiquated parts and improve security Dec-24 Nov-25 Minimal, contractors on doors causing noise Facilities and Operations Danny Holland hollandd@marshall.edu Shock & Awe project
Smith Hall/ Henderson Center Concrete Works Replace broken, loose concrete to improve safety May-24 Nov-25 HC steps blocked off Facilities and Operations Danny Holland hollandd@marshall.edu Shock & Awe project

Smith Music

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding

Athletics

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Tennis Courts Crack Repair 25-Aug 25-Aug Athletics Andrew Brown brown613@marshall.edu Athletic Budget
Golf Bay – Guyan Buildout of 4-bay indoor/outdoor golf hitting bay facility at Guyan Country Club hitting range

School of Medicine

Project Name Description Start Date Finish Date Impact Dept. Project Contact Project Contact Email Funding
Douglass Centre Gym Roof Repair Repair of roof due to extensive storm damage May-25 Aug-25 School of Medicine Jamey Montgomery montgomerych@marshall.edu
Coon Education Building Chiller Replacement Jun-25 Dec-25 School of Medicine Jamey Montgomery montgomerych@marshall.edu